"We need to understand what we want to do: we will probably not restore all the equipment because not everything was new, not everything was upgraded, and we will need to build a new one. This is our opportunity to modernize the power system faster than we planned in Last year, "Sakharuk said. According to him, instead of a substation in the territory of 50 ha "you can build contact distribution devices based on new technologies" that will occupy much less territory.
"This is a 100 m building that replaces the entire large substation. It is more expensive in terms of construction, but it is more reliable and durable, it is automatic inclusion, exception, it is a completely different level of automation and a completely different level of reliability," - explained the executive director DTEK. He also noted that the complete restoration of all the destroyed objects will need "one year to two, and maybe even more.